Promised vs. Produced Tracker · Ohio · as of Q3 2026

Ohio has been promised 5 factories since 2017. 3 are producing.

7th of 33 states by announced capital · 3rd of 17 by share producing, among states with three or more promises

5 promises · $28B announced · 3 producing · 1 not yet producing · 1 cancelled or closed

Intel Ohio One (Silicon Heartland) New Albany · $20.0B · Under constructionL-H Battery Company Plant (Jeffersonville, Ohio) · $3.5B · ProducingUltium Cells Lordstown, Ohio · $2.3B · ProducingCleveland-Cliffs Middletown Works green-steel DRI project · $1.3B · CancelledAnduril Arsenal-1 (Pickaway County, Ohio) · $1.0B · ProducingUltium Cells Lordstown, OhioIntel Ohio One (Silicon Heart…Anduril Arsenal-1 (Pickaway C…L-H Battery Company Plant (Je…Cleveland-Cliffs Middletown W…
producing not yet producing cancelled or closedmark area · announced capitalSites placed at the town · the largest promises are named · a mark opens its row

Ohio, promise by promise

Largest announced capital first. Each row links to its announcement and to the source for its latest status.

announcement to promised first output past the promised date, not producing producing × promise cancelled or closed
  1. Intel Ohio One (Silicon Heartland) New Albany

    Semiconductors · OH

    $20.0B · 3,000 jobs · announced Jan 2022 · promised 2025 · first output: not yet

    sources · promise intc.com · status wosu.org

    Wrong? Correct it on GitHub or email us

    Under construction1y 3m past promise
  2. L-H Battery Company Plant (Jeffersonville, Ohio)

    Battery · OH

    $3.5B · 2,200 jobs · announced Oct 2022 · promised 2025-Q4 · first output 2026-07-02

    sources · promise global.honda · status upi.com

    Wrong? Correct it on GitHub or email us

    Producing8m late
  3. Ultium Cells Lordstown, Ohio

    Battery · OH

    $2.3B · 1,100 jobs · announced Dec 2019 · no promised date · first output 2022-08

    sources · promise cnbc.com · status gmauthority.com

    Wrong? Correct it on GitHub or email us

    Producingno promised date on record
  4. Cleveland-Cliffs Middletown Works green-steel DRI project

    Steel · OH

    $1.3B · 170 jobs · announced Mar 2024 · no promised date · first output: none, cancelled

    sources · promise clevelandcliffs.com · status ohiocapitaljournal.com

    Wrong? Correct it on GitHub or email us

    Cancelledoriginal promise not kept
  5. Anduril Arsenal-1 (Pickaway County, Ohio)

    Aerospace and Defense · OH

    $1.0B · 4,008 jobs · announced Jan 2025 · promised 2026-07 · first output 2026-03

    sources · promise manufacturingdive.com · status jobsohio.com

    Wrong? Correct it on GitHub or email us

    Producing4m early

Dates follow the announcement's own precision: a year with no month is drawn at mid-year, a quarter at its middle month. A person has checked every figure here against its sources, and every check is public. We log every correction made after publication, with its reason.

Other states: Texas New York Louisiana Arizona North Carolina Georgia Michigan Virginia Indiana Tennessee Idaho Iowa Kentucky Alabama Wisconsin South Carolina Utah Pennsylvania Kansas California Oklahoma Illinois Nevada New Mexico Arkansas Mississippi West Virginia Oregon South Dakota Montana Delaware Nebraska

The next recount

Get the recount when we publish it.

We recount every promise each quarter. The next one is due at the end of Q4 2026.

How we collected this
Data: Promised vs. Produced Tracker, 165 promises at the $1B or 2,000 direct jobs floor across 33 states, verified through 2026-10-03 · A person verified every promise against its sources, and we have logged 88 corrections · 165 of 165 carry both a promise source and a status source · map: Census cartographic boundaries via us-atlas, AlbersUSA · We placed each site at its town by hand and drew the bars and marks from the Tracker, without a chart library